A $121-million industrial project is one step closer to being built in both Bulloch and Bryan counties.
The proposed warehouse development passed its first hurdle, Nov. 17, after the Bryan County Planning and Zoning Commission voted unanimously to recommend approving the required rezoning from Agricultural to General Industrial.
The project, proposed by Portman Industrial LLC, is split by the Bulloch/Bryan county line and contains three Class A warehouse facilities, totaling about 2.1 million square feet. The facility is expected to generate $831,500 in Bryan County and $259,600 in Bulloch County along with an estimated 560 full-time employees at full build-out.
The development was significant enough to require a Development of Regional Impact application to the Coastal Regional Commission, which issued its final report in October.
Robert McCorkle, an attorney representing Portman Industrial, cited the nearby Hyundai Motor Group Metaplant America and the growing Port of Savannah as the drivers of the demand for increased warehouse space.
Stacy Watson, the Bryan County Planning and Zoning Commission’s vice chairman and the Georgia Ports Authority’s director of economic development echoed this need to the board.
“We (the Port of Savannah) plan to grow at a rate of about 4.5-5% per year,” Watson said, Nov. 17. “For every container that we move, it means about 25 square feet of industrial spaces needed.”
Construction of the site will take about two to three years, which Watson said will align well with the Port’s needs.
Bulloch County portion
The project proposal will go in front of Bryan County commissioners in December. Pending their approval, the developer said the proposal will then be brought to Bulloch County.
McCorkle said it will be possible for the project to only include the Bryan County portion.
The development will most likely require an intergovernmental agreement between the two counties, especially pertaining to water and wastewater needs. McCorkle said while this infrastructure is available at the site, wastewater will “need some work.”
Environmental concerns
Still, environmental groups and area residents alike have expressed concern about continuous warehouse development.
County planning and zoning staff acknowledge single family homes adjacent to the proposed site, which will face the “most significant” impacts to the rezoning of the land.
The Ogeechee Riverkeeper, an environmental advocacy group, submitted comment to the CRC, urging Bryan and Bulloch leaders to reject the project proposal.
“The current conditions on the site make it very poorly suited for the proposed development,” the group’s submitted statement read. “The floodplains and wetlands present on the properties highlight the site's propensity for flooding, which will be exacerbated by the proposed development.”
A portion of the property is located in a Special Flood Hazard Area.
Project engineers said storm water will also be rerouted to Black Creek, following an existing drainage path.
“If the project is to proceed, ORK urges Bryan and Bulloch counties to fully consider present conditions as well as future risks and require a significant redesign and reduction of the build-out to avoid current flooding risk and reduce additional flood risk from the construction,” the Ogeechee Riverkeeper’s comments read. “In addition, preserving already-existing natural flood controls and requiring additional stormwater control capacity should be considered and added as a condition.”
Damon Mullis, the Ogeechee Riverkeeper’s executive director, said much of undeveloped North Bryan contains wetlands. He said development on top of these essential ecosystems changes the hydrology of an area and creates risks for flooding, wildlife and groundwater health.
His group and other organizations like The Savannah Riverkeeper and One Hundred Miles have been tracking rapid warehouse development across the region. These groups launched a dashboard to showcase warehouse development across southeast Georgia, giving residents the ability to monitor the industrial projects.
Ben Kirsch, the legal director for the Ogeechee Riverkeeper, said the region saw a 50% increase in the amount of warehouse space between 2022 and 2024, going from about 100 million square feet of warehousing to 150 million.
The Ogeechee Riverkeeper also points to a 10% vacancy rate of existing warehouses, questioning the need to construct more.
Watson said warehouse construction and vacancy is cyclical.
“Right now it’s a 10% vacancy, five years ago it was 2-3%. What you see is a cycle of building, vacancy rates go up and then construction stops,” he said.
McCorkle said a project of this scale and in the North Bryan area won’t be at risk of staying vacant. He also emphasized that this land falls under Bryan County’s Comprehensive Plan, which slates the site for industrial use.
“We do believe that market exists,” he said. “What we don’t really have a market for is agricultural property in this location or for large lot single family residential in this location. This site has been vacant, unused for some time. We do believe this is the highest and best use for this property.”
Lucille Lannigan is a growth and development reporter for Morris Multimedia, which owns the Statesboro Herald, Bryan County News, Coastal Courier and Effingham Herald.